How Does the Construction Submittal Review Process Work?

By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15

In the submittal process, the contractor submits product data, shop drawings, and samples proving proposed items meet the specs; the design team reviews and stamps each approved, approved-as-noted, revise-and-resubmit, or rejected. It's the verification gate that keeps non-compliant materials and equipment out of the building.

I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.

Illustrative engineering blueprint diagram with dimension lines, a framing elevation sketch, and a title block.

The concise answer

The submittal process is how the contractor proves that the materials, equipment, and shop drawings they plan to use match what the specifications require — and how the design team verifies that before anything is ordered or installed. The contractor submits product data, samples, and shop drawings; the engineer or architect reviews each against the contract documents and returns it stamped approved, approved-as-noted, revise-and-resubmit, or rejected. The process exists because specifications describe requirements, not specific products — the contractor chooses the actual manufacturer and model. Without submittal review, that choice happens in a vacuum, and the first time anyone checks compliance is when the wrong equipment arrives on a truck.

The workflow from submission to stamp

It starts with the submittal schedule, prepared early in construction, listing every required submittal and its timing relative to procurement lead times. Long-lead equipment — switchgear, chillers, elevators — gets submitted first because its approval gates ordering and its delivery gates everything downstream. Each submittal arrives with the contractor's own review stamp first — the contractor must check it before the designer sees it. The design team reviews for conformance with the contract documents: capacities, ratings, dimensions, listings, and coordination with related systems. The returned stamp dictates next steps, and the whole cycle is logged so nothing falls through. On MEP-heavy projects, the engineer's submittal review is where system compatibility gets verified — the chiller, pumps, and controls all have to work as a system, not just as compliant individual products.

Keeping submittals off the critical path

Submittals delay projects when they're treated as paperwork instead of procurement gating. The practices that keep review moving.

  • Build the submittal schedule around procurement lead times — longest lead items submitted first
  • Require the contractor's review stamp before design review; unreviewed submittals get returned unchecked
  • Submit complete packages: partial submittals for interdependent systems can't be properly reviewed
  • Track every submittal in a log with dates — lost submittals are a top source of schedule disputes
  • Reserve the full contract review period in the schedule; don't plan procurement on optimistic turnaround
  • Treat revise-and-resubmit as a failure to prevent — coach the contractor on what complete looks like

What else do project teams ask?

What are the submittal review stamps and what do they mean?
Approved means proceed as submitted. Approved-as-noted means proceed incorporating the reviewer's corrections. Revise-and-resubmit means fix the deficiencies and send it back — don't order yet. Rejected means start over; the proposed item doesn't comply. Only the first two authorize procurement.
How long does submittal review take?
Contracts typically allow 10 to 15 working days per review round, and complex equipment submittals can take the full allowance. The schedule killer is revise-and-resubmit cycles — each round restarts the clock. Complete first submittals are the fastest path through.
Does submittal approval relieve the contractor of responsibility?
No — and this is widely misunderstood. Review is for general conformance with design intent, not a detailed check of every dimension. The contractor remains responsible for means, methods, quantities, and coordination. Approval doesn't transfer liability for a wrong item.
What are shop drawings versus product data?
Product data is manufacturer literature proving the proposed product meets the spec. Shop drawings are custom fabrication drawings — steel details, ductwork layouts, millwork — showing exactly what will be built. Both go through submittal review; shop drawings get the deeper engineering check.

Ready to discuss your engineering scope?

Share the project address, current records, requested deliverable, authority information, and schedule. Apex Grid confirms professional responsibility, availability, and scope before work begins.

Request a Project Review

Get a quote on your project

Reviewed and sealed by licensed PEs. “Solid engineering and clear communication from start to finish.” — Jason Mitchell, Principal Architect

Tell us what you need and where the project is — quotes back within 12–24 hours on qualifying scopes.