What Are Deferred Submittals in the Permit Process for Projects

By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15

Deferred submittals are designated portions of a project's construction documents that the authority having jurisdiction permits to be designed, reviewed, and approved after the main permit is issued. The engineer of record identifies the deferred items, states the design criteria they must satisfy, reviews the deferred submittals for general conformance, and the deferred work cannot be installed until its submittal is approved.

I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.

Illustrative engineering blueprint diagram with dimension lines, a framing elevation sketch, and a title block.

The concise answer

Deferred submittals are designated portions of a project's construction documents that the authority having jurisdiction permits to be designed, reviewed, and approved after the main permit is issued. The engineer of record identifies the deferred items, states the design criteria they must satisfy, reviews the deferred submittals for general conformance, and the deferred work cannot be installed until its submittal is approved. The discipline is in the criteria. A deferred item with vague performance requirements comes back as a design that doesn't fit — loads the structure wasn't sized for, anchorage the slabs can't provide. Specific criteria on the permit drawings are what make deferral work.

How deferral works in practice

The process starts at permit submittal: the engineer of record lists each deferred item on the drawings with the design loads, performance criteria, and applicable codes the deferred design must meet, and the building official approves the deferral as part of the permit. That list is a contract — items not listed can't be casually deferred later. When the deferred design is ready, its engineer submits it to the engineer of record for the conformance review, then to the jurisdiction for plan check under the deferred submittal process with its own fees and review time. The contractor sequences the work so deferred approvals land before installation. I've seen schedules collapse when teams treated deferred review as instantaneous — the jurisdiction's queue doesn't care about your critical path.

What the engineer must document

Deferral creates paperwork obligations on both sides. The engineer of record's responsibilities include these.

  • Deferred item list on the permit drawings with design criteria, loads, and applicable codes
  • Jurisdiction approval of the deferral request following local procedures and fees
  • Conformance review of each deferred submittal against the stated criteria before forwarding
  • Coordination of deferred designs with the base building structure and systems
  • Construction sequencing that holds deferred work out until approvals are in hand

What else do project teams ask?

What items are commonly deferred?
Fire sprinkler and fire alarm shop drawings, structural steel connections or stairs, curtain wall and storefront engineering, prefabricated truss layouts, and specialty equipment supports. The common thread is work designed by specialty engineers or contractors after the base building permit — items with their own design cycle that would otherwise hold up the whole project.
Does the engineer of record review deferred submittals?
Yes — that's a defined responsibility, not a courtesy. The engineer of record reviews the deferred submittal for conformance with the design intent and the criteria stated on the permit drawings, then forwards it to the building official with a notation of conformance. The deferred designer still owns their design; the engineer of record confirms it fits the building.
Can deferred work be installed before approval?
No. The code is explicit: deferred submittal items cannot be installed until the building official approves the deferred documents. Installing early risks stop-work orders and removal. The construction schedule has to carry the deferred review time honestly instead of pretending the approval is a formality.
Do all jurisdictions allow deferred submittals?
Most do under the building code's provisions, but each jurisdiction sets its own procedures, fees, and limits on what's deferrable. Some restrict deferrals tightly; others handle them routinely. The engineer confirms the local process during permit planning so the deferred list matches what the jurisdiction will actually accept.

Ready to discuss your engineering scope?

Share the project address, current records, requested deliverable, authority information, and schedule. Apex Grid confirms professional responsibility, availability, and scope before work begins.

Request a Project Review

Get a quote on your project

Reviewed and sealed by licensed PEs. “Solid engineering and clear communication from start to finish.” — Jason Mitchell, Principal Architect

Tell us what you need and where the project is — quotes back within 12–24 hours on qualifying scopes.