What Is a Drywell and How Is It Designed for Stormwater?

By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15

A drywell is an underground infiltration chamber that disposes of stormwater by percolating it into the surrounding soil. Design requires infiltration testing to confirm the soil rate, sizing the chamber's storage and infiltrative surface for the design storm, providing pretreatment to keep sediment out, and maintaining required separations to groundwater, foundations, and wells.

I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.

Illustrative diagram of a civil site plan: grading contours around a building pad, a roadway, and storm drainage.

The concise answer

A drywell is an underground infiltration chamber that disposes of stormwater by percolating it into the surrounding soil. Design requires infiltration testing to confirm the soil rate, sizing the chamber's storage and infiltrative surface for the design storm, providing pretreatment to keep sediment out, and maintaining required separations to groundwater, foundations, and wells. The appeal is obvious: no surface land consumed, no outlet to maintain, and the water recharges the aquifer instead of burdening the storm system. The catch is equally obvious: the entire system depends on the soil's willingness to accept water, forever. Everything in the design — the testing, the safety factors, the pretreatment, the separations — exists to make sure that bet is a safe one.

Sizing and testing

The infiltration test is the foundation of the design, and it has to be done right: at the actual proposed depth, in the actual soil the drywell will sit in, with the test method the jurisdiction recognizes. I apply the jurisdiction's safety factor to the measured rate — that factor accounts for long-term clogging and test variability — and design to the factored rate. The storage calculation treats the drywell as a small reservoir: inflow from the design storm minus infiltration during the storm equals the required storage volume. The drain-time check then confirms the full volume empties within the allowed window. If it doesn't, the options are more drywells, a bigger chamber, or a different disposal method. Forcing a drywell onto a site that fails the drain-time check is how you get a system that works for one season.

Keeping a drywell alive

Drywells don't fail loudly — they fail by slowly losing infiltration capacity until a big storm backs water up where it was never supposed to go. The maintenance and protection details are the design. Here's what keeps drywells working for decades.

  • Test honestly: infiltration testing at the right depth and location, with the jurisdiction's safety factor applied
  • Pretreat everything: catch basin sumps or separators upstream to keep sediment out of the chamber
  • Protect during construction: keep construction sediment and equipment loads away from the drywell area
  • Provide observation access: a way to check water levels and confirm the system drains between storms
  • Plan for the end of life: even maintained systems lose capacity over decades — design access for rehabilitation

What else do project teams ask?

How do you know if the soil is suitable for a drywell?
Through infiltration testing — typically a double-ring infiltrometer or a pit test at the proposed drywell depth, witnessed per local standards. The measured rate, divided by a safety factor the jurisdiction sets (often 2), gives the design rate. Sandy and gravelly soils work; clay doesn't. High groundwater kills the concept because there's nowhere for the water to go.
How big does a drywell need to be?
Big enough to store the design storm volume and infiltrate it within the required drain time — commonly 48 to 72 hours. The engineer computes the tributary runoff, sizes the chamber storage, and checks that the infiltrative surface area times the design infiltration rate can empty it in time. Bigger storms or slower soils mean bigger or multiple drywells.
Do drywells need pretreatment?
Yes — sediment is the enemy of every infiltration system. A catch basin sump, a vegetated swale, or a proprietary separator upstream keeps the fines out of the drywell. Without pretreatment, the infiltrative surfaces blind over within a few years and the drywell stops infiltrating. I consider pretreatment mandatory, not optional.
What separations does a drywell require?
Typical minimums: 10 feet from building foundations, 100 feet from drinking water wells, and several feet of separation from seasonal high groundwater — commonly 3 to 10 feet depending on the jurisdiction. These protect structures from saturation and groundwater from contamination, and they're permit conditions, not suggestions.

Ready to discuss your engineering scope?

Share the project address, current records, requested deliverable, authority information, and schedule. Apex Grid confirms professional responsibility, availability, and scope before work begins.

Request a Project Review

Get a quote on your project

Reviewed and sealed by licensed PEs. “Solid engineering and clear communication from start to finish.” — Jason Mitchell, Principal Architect

Tell us what you need and where the project is — quotes back within 12–24 hours on qualifying scopes.