What Is a Construction Change Order and How Do You Handle One?
By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15
A change order is a written amendment to the construction contract adjusting scope, price, and schedule. Handle them with a strict process: every change in writing, priced and approved before the work is performed. Expect some on every project; control them with documentation, not trust.
I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.
The concise answer
A change order is a formal written amendment to the construction contract that changes the scope, price, schedule, or all three — and the key word is formal. Verbal 'just do it' instructions are where owners lose money and contractors lose payment leverage. Legitimate change orders come from three sources: owner-requested changes, unforeseen conditions like bad soils or hidden structural damage, and design gaps or errors. The right mindset is management, not elimination. A project with zero change orders either had perfect documents and zero surprises — rare — or has costs buried somewhere they'll surface later. Budget a contingency, run a tight process, and judge each change on its merits.
The three sources and how to treat each
Owner changes are your choice and your cost — the discipline here is deciding deliberately, with the price and schedule impact in front of you before you say yes. Small 'while you're at it' requests compound; batch them and price them together. Unforeseen conditions are nobody's fault: rock where the borings showed soil, asbestos in the walls, a rotted beam behind the plaster. The contract should define how differing site conditions are handled, and the geotechnical report plus exploratory demolition are your pre-construction defenses. Design gaps are the preventable category. Incomplete details, uncoordinated MEP and structure, missing dimensions — these generate the RFIs that become change orders. This is where design fee savings evaporate: every dollar saved on coordination returns as several dollars in field changes.
The change-order control process
Process beats vigilance. Set this up in the contract and enforce it from day one. Non-negotiable elements of change control.
- Written change requests only — no verbal authorizations, no 'we'll paper it later'
- Priced before performance: itemized labor, materials, equipment, and markup disclosed
- Schedule impact stated on every change order, even if the answer is zero days
- A single authorized approver on the owner side with a dollar threshold for escalation
- Monthly change-order log reviewed against contingency — track the burn rate
- Emergency exception defined narrowly: safety and property protection only, documented within 24 hours
Which related engineering resources can help?
What else do project teams ask?
What percentage of a project should change orders be?
Can a contractor do the work first and price it later?
Who pays when the drawings were wrong?
How do I know a change order price is fair?
Ready to discuss your engineering scope?
Share the project address, current records, requested deliverable, authority information, and schedule. Apex Grid confirms professional responsibility, availability, and scope before work begins.
Request a Project Review