How Are Emergency Generators Sized for Toll Plaza Sites?

By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15

Toll plaza generators are sized from a real critical-load inventory with motor-starting analysis, automatic sequenced transfer bridged by UPS, and fuel storage matched to the agency's required outage runtime.

I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.

Illustrative diagram of building MEP systems: ductwork with diffusers, an electrical panel with conduit, and piping runs.

Sizing from the load inventory

Generator sizing starts with a spreadsheet, not a guess. I list every load the generator will carry with its running kilowatts, power factor, and starting characteristics — and motor starting is where plazas get interesting, because HVAC compressors and gate operators pull locked-rotor current that can dip voltage enough to reboot sensitive electronics. The generator is sized so the largest starting step stays within the voltage-dip limits the collection equipment tolerates, with the transfer sequence staggering starts to keep the steps manageable. I also check the generator against the UPS recharge load and any harmonic content from the electronic loads. The result is a machine that starts clean, picks up load in order, and runs steady — which is the entire job description.

Transfer sequencing and fuel reliability

The automatic transfer switch is programmed with the plaza's priorities: collection and communications first, booth HVAC next, then lighting and the remaining loads in sequence. I coordinate the UPS autonomy with the generator's start-and-transfer time so the electronics never see the gap, and I specify bypass-isolation transfer switches where the agency needs to service the switch without dropping the plaza. On the fuel side, the tank is sized for the required runtime at real load, with containment, leak detection, and fuel polishing or scheduled turnover so the diesel does not go stale. A generator with bad fuel is a very expensive paperweight, and I design the fuel system so that failure mode does not happen.

Toll plaza generator design checklist

A toll plaza generator design is complete when it clears this checklist. Backup power that does not start, transfer, or run long enough is not backup power. • Generator sized from a real load inventory with motor-starting voltage-dip analysis • Sequenced automatic transfer with UPS bridging so collection never sees an interruption • Fuel storage matched to the agency's required runtime with containment and fuel maintenance • Enclosure sited for exhaust dispersion away from booth intakes and clear service access • Loaded test provisions and a written test schedule the maintenance crew can execute

What else do project teams ask?

What loads must a toll plaza generator carry?
Everything the plaza needs to keep operating: toll collection terminals and lane equipment, barrier gates, lane signals, booth HVAC, canopy and site lighting, communications and network gear, and CCTV and security. I inventory each load's running and starting characteristics, then designate which transfer first and which can shed if the generator is ever overloaded. The honest inventory usually surprises owners — the collection electronics are a modest load, but the HVAC and lighting across a multi-lane plaza add up fast.
How long should the generator's fuel supply last?
For the outage duration in the agency's continuity plan, which for toll facilities is commonly measured in days rather than hours — a plaza that goes dark during an extended outage creates both a revenue and a traffic-management crisis. Remote plazas get larger storage because fuel delivery may be impossible during the same storm that caused the outage. I size the tank for the required runtime at the actual generator load, add the code-required containment, and specify fuel maintenance so stored diesel is actually usable when needed.
Where should the generator be located at a toll plaza?
Close enough for short feeder runs to the transfer equipment, but positioned so exhaust never reaches booth ventilation intakes and noise does not disturb operations or neighbors. I keep it outside the clear zone or behind proper barrier protection, on a concrete pad with containment for fuel and fluids, with clear service access on all sides. The enclosure is weatherproof and sound-attenuated, and the location is coordinated with the site drainage so the pad never sits in ponded water.
How is generator testing handled for toll sites?
With scheduled loaded testing that proves the machine without disrupting operations. I specify automatic monthly exercise plus periodic full-load bank testing, with the transfer test sequenced so collection loads prove out on generator power. The design includes the load bank connection point so testing does not require jury-rigged cables. Test logs become part of the facility's compliance record, and I make sure the testing procedure is written for the maintenance crew that will actually perform it.

Ready to discuss your engineering scope?

Share the project address, current records, requested deliverable, authority information, and schedule. Apex Grid confirms professional responsibility, availability, and scope before work begins.

Request a Project Review

Get a quote on your project

Reviewed and sealed by licensed PEs. “Solid engineering and clear communication from start to finish.” — Jason Mitchell, Principal Architect

Tell us what you need and where the project is — quotes back within 12–24 hours on qualifying scopes.