What Does TMS 402 Require for Structural Masonry Design?

By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15

TMS 402/602 is the IBC-adopted masonry code and construction specification, covering allowable stress and strength design of masonry plus field inspection levels tied to risk and seismic categories — since masonry quality must be verified during construction.

I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.

Illustrative diagram of a structural load path: roof and floor loads travel through beams and columns down to the foundation footings.

The concise answer

TMS 402 requires engineers to design masonry for the applicable loads using either allowable stress or strength design, covering compressive, flexural, and shear capacity of walls, columns, pilasters, and beams — with grout, mortar, and reinforcement specified to match the design assumptions. TMS 602 then requires the construction to be built and inspected to those assumptions, with inspection levels set by tables keyed to risk category and seismic design category. The practical consequence is that masonry engineering is a two-part deliverable: calculations and drawings that satisfy 402, plus specifications and an inspection plan that satisfy 602. Projects get in trouble when the design assumes fully grouted, inspected reinforced masonry but the specs and inspection plan describe something lighter. We keep the design assumptions, the specs, and the inspection level explicitly linked so the wall that gets built is the wall that was designed.

Why masonry lives or dies in the field

Unlike steel, which arrives from the shop with mill certs, or concrete, which gets cylinder breaks, masonry's quality is created on the scaffold — one unit, one mortar joint, one grout lift at a time. Low-lift grouting versus high-lift grouting changes what's inspectable. Reinforcement that's supposed to be centered in the cell but ends up against the face changes the wall's capacity. Mortar mixed too wet loses strength. Every one of these is invisible once the wall is finished, which is exactly why the inspection tables exist. Our approach is to make the field requirements unmistakable: grout lift heights on the drawings, cleanout locations for high-lift grouting, inspection hold points in the specs, and preconstruction meetings where the mason and inspector walk through the requirements together. Masonry done right is durable, economical structure — but 'done right' has to be verified while the work is open, not assumed afterward.

Masonry project checklist

Address these before masonry construction starts and the walls go up without surprises.

  • Select the design method and confirm the masonry shear wall type suits the Seismic Design Category
  • Set the TMS 602 inspection level from the risk category and SDC, and show it in the documents
  • Specify grout type, lift heights, and cleanout requirements the mason can actually build
  • Detail reinforcement placement with tolerances that keep bars where the design assumes
  • Coordinate veneer anchorage and support separately from the structural backup wall
  • Hold a preconstruction meeting with the mason and inspector on grouting and hold points

What else do project teams ask?

Allowable stress vs. strength design for masonry — which is used?
Both are permitted by TMS 402. Allowable stress design compares service loads against allowable stresses and remains common for simpler masonry. Strength design uses factored loads and reduced nominal strengths, paralleling concrete design, and is more common for engineered structures and seismic force resisting systems. Our engineers select the method that fits the project's complexity and the reviewer's expectations in the jurisdiction.
What is the difference between TMS 402 and TMS 602?
TMS 402 contains the design requirements — how engineers calculate masonry capacity for axial, flexure, and shear. TMS 602 contains the construction and specification requirements — materials, mortar and grout, construction practices, tolerances, and the inspection tables. They're adopted together because a masonry design is only as good as its construction, and the inspection tables in 602 are what enforce that link.
Does all masonry work require special inspection?
Not all of it, but most structural masonry does. TMS 602 sets three inspection levels with required tasks — verifying mortar, grout, reinforcement placement, grout space, and unit placement — and the applicable level rises with the building's risk category and seismic design category. Veneer and nonstructural masonry have lighter requirements, but anything carrying structural load should expect inspection.
Can masonry be used for a building's seismic force resisting system?
Yes. Reinforced masonry shear walls are a recognized seismic force resisting system, with detailing requirements that escalate by Seismic Design Category — from ordinary reinforced masonry in lower categories to special reinforced masonry shear walls with strict reinforcement and grouting rules in higher ones. Unreinforced masonry is heavily restricted in seismic regions, which is why existing unreinforced buildings often need retrofit.

Ready to discuss your engineering scope?

Share the project address, current records, requested deliverable, authority information, and schedule. Apex Grid confirms professional responsibility, availability, and scope before work begins.

Request a Project Review

Get a quote on your project

Reviewed and sealed by licensed PEs. “Solid engineering and clear communication from start to finish.” — Jason Mitchell, Principal Architect

Tell us what you need and where the project is — quotes back within 12–24 hours on qualifying scopes.