How Are Electrical Service Upgrades Planned for RV Parks?
By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15
RV park service upgrades are planned in phases: metering the existing service through a peak period to find real capacity, sizing a new service for current plus future demand with early utility coordination, then building the new distribution alongside the old and transferring sites in groups during low occupancy — so guests never lose power.
I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.
Studying the existing system
I document what exists before designing what comes next: the service size and configuration, the distribution layout, the condition of panels, feeders, and pedestals, and the grounding system's integrity. The metering data reveals the real demand profile and any power quality problems the new design must fix — chronic undervoltage, for instance, might trace to long undersized feeders that the upgrade replaces. I also review the park's history: which sections trip, which pedestals fail, where maintenance spends its time. The upgrade design fixes the known pain while adding the capacity for growth, and the study ensures the new service is sized to evidence rather than anxiety.
Designing the new service and phasing
The new service gets sized for the measured peak plus the owner's growth — new sites, larger rigs, EV charging, amenities — with the demand factors that keep it economical. I lay out the new distribution to modern standards: properly placed transformers, looped or radial feeders with spare capacity, new pedestals with individual protection, grounding and surge protection throughout. The phasing plan sequences construction around occupancy: build the new service first, extend distribution section by section, transfer sites in groups during shoulder periods, and decommission the old system last. Each phase leaves the park fully operational, and I build float into the schedule for the utility's work.
Checklist for an invisible upgrade
I verify the upgrade the way guests will experience it: voltage measured at the farthest pedestal on a peak evening, every new breaker and GFCI tested, the old system safely decommissioned with nothing energized that shouldn't be. The utility's inspection and sign-off happen on their schedule, which I've built into the plan. The owner gets updated as-builts, the new panel schedules, and the maintenance baseline for the modernized system. Here is the checklist I hand RV park owners planning an upgrade.
- Meter the existing service through a peak period to establish real demand and power quality
- Size the new service for measured peak plus documented growth with proper demand factors
- Coordinate with the utility early on service location, transformer, metering, and timeline
- Phase construction so the park stays open: build new alongside old, transfer in groups
- Verify voltage at the farthest pedestal under peak load and safely decommission the old system
Which related engineering resources can help?
What else do project teams ask?
How do you know when an RV park needs a service upgrade?
What does a load study involve?
How is the utility involved in a service upgrade?
Can the park stay open during the upgrade?