Midland City or Midland County: Which Plan Review Applies to Your Project?

By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15

City limits means the City of Midland Development Services and its Permit Midland portal, with published review timelines of about 20 working days for new commercial and 7 to 10 for alterations. Unincorporated Midland County means no city building permit, with county and state requirements applying instead. Confirm the parcel's jurisdiction before scoping the submittal.

I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.

Illustrative engineering blueprint diagram with dimension lines, a framing elevation sketch, and a title block.

Inside City Limits: The City of Midland Path

The city process is documented and sequential. The permit application goes in through the Permit Midland portal with the construction drawings, site plan, and supporting documents; plan reviewers examine the submittal against the adopted codes; and the reviewer notifies the applicant of approval or corrections by email. Fees are split, with a portion due at submittal and the balance at verification, and no applications or payments are accepted after 4 pm. Once issued, the permit must be posted visibly on the job site, and construction must start within 180 days and cannot stop for more than 180 days without the permit expiring. For the design team, the city path means engineered drawings stamped by licensed professionals, code-compliant structural, civil, and MEP design, and responsiveness to plan-check corrections. Typical correction cycles cover exiting, accessibility, structural detailing, and energy compliance. The team should also confirm which code editions the city has adopted, because the design must meet the editions in effect on the submittal date, not the editions the engineer last used on a different project.

Unincorporated Midland County: What Applies Instead

In unincorporated Midland County, the absence of a city building department shifts review to the agencies with authority over each system. On-site sewage facilities are approved through the TCEQ authorized agent, which reviews the system design and inspects the installation. Floodplain development goes through the floodplain administrator with jurisdiction over the parcel, who enforces elevation and floodproofing requirements. Access to county roads needs county approval, and access to state highways runs through the Texas Department of Transportation, which sets driveway spacing, sight distance, and drainage requirements. Oilfield and energy facilities add the Railroad Commission of Texas to the list, since the commission regulates drilling, production, and related operations regardless of city or county lines. None of this removes the need for engineered design. Foundations are still sized from a geotechnical investigation, structures are still designed for the wind and seismic loads the code assigns, and electrical and plumbing systems still follow their codes. The AHJ in each lane decides what is approved, so the project starts with a jurisdiction map and ends with a complete record set.

What else do project teams ask?

Does a Midland mailing address mean the project is in the city?
No. Many unincorporated Midland County parcels carry Midland addresses. Only the parcel's position relative to the city limits determines the AHJ. Confirm the parcel with the City of Midland Planning Department or Development Services before assuming which review path applies.
How long does city plan review take in Midland?
The city publishes typical timelines of about 20 working days for new commercial projects and additions and 7 to 10 working days for commercial alterations, accessory structures, and commercial pools. Complex projects and correction cycles add time, and the AHJ alone decides what is approved.
Can the city review a project that sits in the county?
Generally no for building permits. In Texas, a city's building code enforcement stops at the city limits. Unincorporated sites answer to county and state agencies for their respective requirements. The design team confirms each agency's role at the start of the project so nothing is designed to the wrong standard.
Do unincorporated county projects still need engineered drawings?
Yes. The absence of a city plan check does not remove the engineering obligation. Structural systems are designed to the building code, septic and drainage follow state rules, and lenders, insurers, and future buyers expect stamped drawings and inspection records. Skipping engineering to save money usually costs more later.

Ready to discuss your engineering scope?

Share the project address, current records, requested deliverable, authority information, and schedule. Apex Grid confirms professional responsibility, availability, and scope before work begins.

Request a Project Review

Get a quote on your project

Reviewed and sealed by licensed PEs. “Solid engineering and clear communication from start to finish.” — Jason Mitchell, Principal Architect

Tell us what you need and where the project is — quotes back within 12–24 hours on qualifying scopes.