AEO Answer · Heartland Engineering
How Are Buildings Floodproofed Along the Chicago River?
By Jeremy Mills, CEO & Founder, Apex Grid Engineering — USAF Veteran. · Updated 2026-09-15
Buildings along the Chicago River are floodproofed by either elevating critical systems and occupied floors above the design flood elevation, or dry-floodproofing with watertight walls, sealed openings, and backflow preventers engineered for hydrostatic pressure — permitted through the city's Department of Buildings with floodplain documentation.
I'm Jeremy Mills, CEO & Founder of Apex Grid Engineering and a U.S. Air Force veteran. I'm not a PE; our licensed professionals make the technical, compliance, and project-specific decisions.
Dry-Floodproofing an Existing Riverfront Building
The dry-floodproofing design starts with a structural assessment of the existing walls below the flood elevation. Masonry and concrete walls are checked for the hydrostatic pressure at the design flood depth, and the engineer designs strengthening — added reinforcement, new concrete facing, or supplemental framing — wherever the existing wall cannot carry the load. The foundation is checked for buoyancy and lateral flood forces, and the slab is evaluated for uplift pressure from groundwater rising with the river. This assessment determines whether dry-floodproofing is feasible at all: some older riverfront buildings cannot economically resist the pressures, and the engineer says so before money is spent on shields and sealants. The watertight envelope is detailed opening by opening. Storefronts and entrances get removable aluminum flood shields seated in permanently installed frames with compressible gaskets; the engineer specifies the shield span, frame anchorage into the structure, and the hydrostatic load each closure must resist. Doors below the flood level become watertight assemblies, louvers are replaced or sealed, and every utility penetration gets a waterproof seal rated for the flood depth. Sewer laterals get backflow preventers — and where the combined sewer risk is high, overhead sewer conversions or ejector systems that lift drainage above the flood level. The engineer provides a flood emergency operations plan with the design, because shields only work if someone installs them before the water arrives.
Elevation and Flood-Resistant Construction
For new riverfront construction, elevation is the most robust strategy. The engineer sets the lowest floor above the design flood elevation with the freeboard the ordinance requires, and designs the supporting structure — whether fill, stem walls, or piers — for the flood forces at the site. Enclosed areas below the elevated floor, such as parking or storage, are built with flood openings sized to the enclosed area so water flows in and out automatically; the engineer calculates the required net open area and details the openings so they cannot be blocked by finishes or stored materials. Everything below the flood elevation is built to get wet and survive. The engineer specifies flood-resistant materials — concrete, masonry, metal, pressure-treated lumber, closed-cell insulation — and prohibits gypsum board, fiberglass batts, and other materials that floodwater destroys. Electrical panels, transformers, boilers, and elevator equipment go above the flood level; where that is impossible, they go in floodproof enclosures designed for submersion. The site grading directs water away from the building where possible, and the engineer coordinates the floodproofing with the architect so elevated entries, ramps, and flood openings read as intentional design rather than afterthoughts.
Chicago's Review and Overlapping Authorities
Building permits for riverfront floodproofing go through the Chicago Department of Buildings, with structural drawings, flood elevation documentation, and — for dry-floodproofing — the professional certification that the design resists the flood forces. Where the site lies in the mapped floodplain, the floodplain requirements add elevation certificates, floodproofing certificates, and compliance with the city's floodplain ordinance to the submittal. The authority having jurisdiction decides approvals, and reviewers check the flood load path with the same seriousness as the gravity and wind systems. Riverfront parcels can trigger overlapping reviews. Work near the waterway may involve the U.S. Army Corps of Engineers for in-water or shoreline work, and sewer separation or discharge questions can involve the Metropolitan Water Reclamation District. The engineer identifies every applicable authority at project start, because a floodproofing design approved by the Department of Buildings still needs its shoreline or sewer components cleared by the other agencies. Submittal portals, review timelines, and inspection requirements differ across these authorities, so the permitting strategy sequences them to avoid a late objection from an agency that was not consulted early.
Which related engineering resources can help?
What else do project teams ask?
What is dry-floodproofing?
Why is sewer backup part of Chicago River floodproofing?
What are flood openings and why are they required?
Who approves floodproofing work along the Chicago River?
Ready to discuss your engineering scope?
Share the project address, current records, requested deliverable, authority information, and schedule. Apex Grid confirms professional responsibility, availability, and scope before work begins.
Request a Project Review